Construction
Rubble Dumpsite - CRD-1
Scope of Work (contd.)
Approximately 2,000 linear feet of riprap-lined
drainage channels intercepted and directed runoff flow to a central level flow discharge
area. After hydroseeding the entire area, erosion control/revegetation matting was placed
on sloped areas. The vegetative cover was monitored and maintained.
Contractor (Hong) provided:
All equipment, tools, materials, supplies
Work force (Project management, equipment operators, laborers)
Hazardous Waste Contract
Scope of WorkUnder the USAF's remedial action plan for Pease, waste was removed from several landfills
within the base confines. Waste included soil and organic material; building debris,
concrete, asphalt; drill spoil containers; discarded personal protective equipment;
miscellaneous landfill materials determined to be contaminated (Heavy metals, ignitables,
PCB's, solvents, poisons, asbestos, etc.); medical and infectious waste.
Contractor (Hong) provided:
Hazardous waste containers and liners (roll-offs, drums and overpacks)
Waste Profile/Identification
Transport Vehicles
Transportation to a licensed disposal facility
Treatment to hazardous wastes as required by 40 CFR 268 and New Hampshire
land disposal restrictions
Disposal of waste in accordance with applicable regulations and acceptance criteria.
Labor, materials, tools, equipment, engineering, procurement and construction
services, technical and professional services, including Health and Safety,
management and supervision, measuring instruments for on-site screening,
training, permitting and planning. |